This is the second phase of the West Nile Delta project, where the field development will be at depths of up to approximately 800 metres.
The contract scope includes engineering, procurement, installation and pre-commissioning of the subsea infrastructure from twelve wells, with 80 kilometres of umbilicals and 220 kilometres of pipelines. It also includes the installation of the export lines from the subsea location to the Idku terminal.
Engineering and project management work will commence immediately and will be undertaken at Subsea 7's Global Projects Centre in London. Offshore installation is scheduled to commence in two stages.
The first stage, commencing in 2017, will comprise the landfall and shallow water pipelay, and the second stage, commencing in 2018, will involve the installation of deepwater pipelines and execution of the SURF scope. Subsea 7 vessels Seven Borealis and Seven Antares will be used for the pipelay, with the heavy construction vessel, Normand Oceanic, being used for the other construction activities.
Øeyvind Mikaelsen, Executive Vice President Southern Hemisphere and Global Projects said: "This major contract awarded by BP recognises our performance during the first phase of the West Nile Delta project and allows us to deliver synergies across multiple work packages. Our early engagement on this project has enabled BP and Subsea 7 together with DEA to develop an optimised solution for the development of the Giza, Fayoum and Raven fields and demonstrates the effective collaboration between us. We look forward to consolidating our presence in Egypt and building on our long and successful relationship with BP."
(1) Subsea 7 defines a major contract as being over USD 750 million.
Subsea 7 S.A. is a leading global contractor in seabed-to-surface engineering, construction and services to the offshore energy industry. We provide technical solutions to enable the delivery of complex projects in all water depths and challenging environments.