SOFIA April 28 (SeeNews) - ICGB, the operator of the Greece-Bulgaria natural gas interconnector (IGB), is planning to launch market tests in the second half of 2023 to gauge potential demand ahead of a planned capacity expansion, chief executive Teodora Georgieva told SeeNews.
ICGB has begun assessing the pipeline's infrastructure readiness to carry hydrogen as well, Georgieva told SeeNews in an interview earlier this month at the Budapest LNG Summit.
In case of sufficient market demand, the expansion of the IGB's capacity to 5 billion cubic metres (bcm) per year from the current 3 bcm/year will also help ensure the flow of liquefied natural gas (LNG) from terminals in Greece - the operational facility at Revithoussa and planned terminals like the one in Alexandroupolis. ICGB is already working on this opportunity with Greek transmission system operator DESFA, according to the chief executive. Building a new compressor station on the Greek side is one of the projects that will advance capacity expansion.