Saturday, October 26, 2019
The Faregh field development Phase 2 is to boost daily production capacity to a quarter-billion cubic feet of gas and 15,000 barrels of condensates
In an important step toward achieving the production targets of the National Oil Corporation (NOC), Waha Oil Company (WOC) announced the beginning of operating tests of the Phase 2 of the Faregh field development project, starting on Wednesday, October 23, 2019 to pump gas to the Intisar 103 field. At a later date, gas will be shipped to the coastal network, to which the field is connected. This step is a significant achievement of NOC and WOC to serve Libyans and the national economy.
Faregh’s gas will be used to increase the efficiency of crude oil production at the Intisar 103 field and could supply the power plants in the Eastern Region, replacing subsidized liquid fuel, a measure that is both cost-saving and environmentally friendly. The project will also increase gas supply to methanol plants and the Libyan Norwegian Fertilizer Company (LifeCo) in Marsa El Brega.
NOC is awaiting the General Company for Gas Transmission & Distribution’s completion of gas pipeline installations to connect the Faregh field with the Sarir power plant, carried out in collaboration with Petrojet, an Egyptian company.
Showing posts with label Faregh Field. Show all posts
Showing posts with label Faregh Field. Show all posts
Saturday, October 26, 2019
Thursday, January 10, 2019
Waha Adds Faregh Field to Libyan Totals - PETROLEUM AFRICA
Thursday, January 10, 2019
Waha Oil Company, a NOC subsidiary, completed preparations on another horizontal well in the Faregh field ahead of the planned start of second-phase experimental gas production. Waha is expected to start the second-phase of experimental gas production at the end of Q1 but was able to move the date forward by almost two months.
According to NOC, the initial tests indicate that the B B-14-59 well is expected to produce up to 24 Mmcf/d of gas, and 1,500 bpd of condensate. This well is in addition to the expected 33 Mmcf/d of gas, and 1,400 bpd of condensate production capacity of well B B-10-59, completed in November 2018.
NOC chairman, Mustafa Sanalla thanked staff dedicated to this project and underlined the importance of a refocused Faregh field to provide gas for local community use, and the fostering of further regional economic development.
Waha Oil Company, a NOC subsidiary, completed preparations on another horizontal well in the Faregh field ahead of the planned start of second-phase experimental gas production. Waha is expected to start the second-phase of experimental gas production at the end of Q1 but was able to move the date forward by almost two months.
According to NOC, the initial tests indicate that the B B-14-59 well is expected to produce up to 24 Mmcf/d of gas, and 1,500 bpd of condensate. This well is in addition to the expected 33 Mmcf/d of gas, and 1,400 bpd of condensate production capacity of well B B-10-59, completed in November 2018.
NOC chairman, Mustafa Sanalla thanked staff dedicated to this project and underlined the importance of a refocused Faregh field to provide gas for local community use, and the fostering of further regional economic development.