Friday, September 27, 2019

TANAP delivers 2.39 billion cubic meters of gas to Turkey as of August - DAILY SABAH

27.09.2019 
BARIŞ ERGIN

The amount of gas the Trans-Anatolian Natural Gas Pipeline (TANAP) has carried to Turkey has reached 2.39 billion cubic meters as of August, TANAP General Manager Saltuk Düzyol said.

"A total of 30%, corresponding to $450 million, of the revenue of $1.45 billion that will be generated when the total transmission capacity is reached, will belong to BOTAŞ [Turkish Petroleum Pipeline Corporation] every year. We predict that TANAP will reach a full transmission capacity of 16 billion cubic meters in two to three years," Düzyol told a group of journalists in Ankara yesterday.

The 1,850-kilometer TANAP forms the backbone of the Southern Gas Corridor, a project to increase and diversify European energy supply by bringing gas resources from the Caspian Sea: Shah Deniz 2 gas from Azerbaijan to Turkey and through Turkey to Europe markets.

Saturday, May 25, 2019

Bulgarian PM Borisov: IGB to Lead to a Real Diversification of Sources - NOVINITE

May 25, 2019, Saturday // 08:57

Interconnector Greece-Bulgaria (IGB), which envisages transportation of Azerbaijani gas to Bulgaria will ensure real diversification of sources, said Bulgaria’s Prime Minister Boyko Borissov, Trend reports.

He made the remarks during a meeting with Greek Prime Minister Alexis Tsipras before the groundbreaking ceremony of the interconnector that took place May 22 in Bulgaria’s Kirkovo.

“The realization of the project for construction of gas interconnection between Bulgaria and Greece will have a key role for the whole region and for Europe. The project is of strategic importance not only for our two countries but also for the whole of Europe, including the countries of the Western Balkans," said the prime minister.

Borissov pointed out that the interconnector will lead to a real diversification of the sources and routes for natural gas supply.

IGB is a gas pipeline, which will allow Bulgaria to receive Azerbaijani gas, in particular, the gas produced from Azerbaijan's Shah Deniz 2 gas and condensate field. IGB is expected to be connected to TAP via which gas from the Shah Deniz field will be delivered to the European markets.

The initial capacity of IGB will be 3 billion cubic meters of gas.

Thursday, September 13, 2018

Bulgaria-Greece Gas Pipeline Project Receives Initial Bids - NOVINITE / REUTERS

September 13, 2018, Thursday // 09:53
Reporting by Tsvetelia Tsolova; Editing by Edmund Blair

Italy’s Saipem, a consortium including Azeri state firm SOCAR and nine other groups or firms have submitted initial bids to build a gas pipeline between Bulgaria and Greece, the company overseeing delivery of the project said.

ICGB launched a tender in April for design, procurement and construction of the 182-km (113-mile) pipeline that is estimated to cost 145 million euros (8 million). The contract winner will have 18 months to complete the project.

Other firms which have filed initial bids also include Italy’s Sicim, Greek company J&P Avax, Turkey’s Fernas, a group including Sicilsaldo, Nuova Ghizzoni and Inrakat, and a consortium of Germany’s Max Streicher and Greece’s Terna.

ICGB will draw up a shortlist of final bidders.

Sofia plans to use the pipeline to receive one billion cubic metres (bcm) of gas per year from Azerbaijan’s Shah Deniz 2 gas field after 2020, ending its almost complete reliance on Russian gas supplies.

Thursday, August 23, 2018

Azeri natural gas sellers book 8.6 Bcm/year long-term capacity to Italy: TAP - S&P GLOBAL PLATTS


Brussels, 23 Aug 2018 | 11:28 UTC
Author: Siobhan Hall; Editor: Alisdair Bowles

  • 10 Bcm/year Greece
  • -Italy TAP gas link to open in 2020
  • Shah Deniz 2 sellers have 25-year capacity contracts
  • TAP to offer short-term capacity in future auctions
Brussels — Azerbaijan's Shah Deniz 2 natural gas field producers have booked around 8.6 Bcm/year of long-term capacity to Italy in the planned 10 Bcm/year Trans-Adriatic Pipeline, developer TAP's head of communication, Lisa Givert, told S&P Global Platts on Thursday.

TAP is the last leg of the so-called Southern Gas Corridor that is to enable Europe to import gas initially from the 16 Bcm/year Shah Deniz 2 field, a new supply source.

Saturday, June 30, 2018

First Gas Deliveries to Turkey Launched Via TANAP Pipeline - SPUTNIK NEWS

30.JUNE.2018, 14:24 

MOSCOW (Sputnik) - Azerbaijan has started first gas deliveries to Turkey via the Trans-Anatolian Pipeline (TANAP), Southern Gas Corridor CJSC General Director Afgan Isayev said in a statement.

"The SGC project has been financially supported by the leading international financial institutions, and Phase-0 under TANAP project, which relates to the works required for the first commercial gas deliveries to Turkey, has already been completed. First commercial gas deliveries to Turkey has commenced today, on 30 June 2018. The works planned for the delivery of natural gas to Europe through Turkey in the near future are being carried out according to the schedule," Isayev was quoted as saying in the statement.

According to the statement, the Multilateral Investment Guarantee Agency (MIGA, part of World Bank group) has approved the loan for the Azerbaijan Republic totaling $750 million to finance the TANAP project.

It will transport gas from the Azerbaijani Shah Deniz Stage 2 gas field to Turkey and Europe.

The target capacity of the TANAP pipeline is 31 billion cubic meters of gas per year. The pipeline is 1,150 miles long.

Saturday, June 23, 2018

A Storm Is Brewing In The Southern Gas Corridor - OIL PRICE



Jun 23, 2018, 4:00 PM CDT
Vanand Meliksetian

No fewer than Turkish President Recep Tayyip Erdogan, Azerbaijani President Ilham Aliyev, Serbian President Aleksandar Vucic and Ukrainian President Petro Poroshenko attended a gathering in Central Turkey on 12 June. The amount and variety of attendees of this meeting reveal a common interest in one field of geopolitical developments: energy and more specifically natural gas.

The opening ceremony of the 1.850 kilometers long Trans Anatolian Pipeline, TANAP, starting at the Shah Deniz gas field in Azerbaijan and ending in Turkey, is the last step before connecting to the European grid in Greece and Italy. TANAP is part of the Southern Gas Corridor, which was the dream of many European leaders and officials to create an alternative to Russian gas.

Tuesday, June 12, 2018

Turkey opens TANAP pipeline that will bring Azeri gas to Europe - DW


12.06.2018

Turkey and Azerbaijan have inaugurated the TANAP pipeline that will bring gas to Europe while bypassing Russia. The project has won political support from both the United States and European Union.

The presidents of Turkey and Azerbaijan have inaugurated a major pipeline that will eventually transport Azerbaijan natural gas to Europe.

The $8.5-billion (€7.2 billion) Trans-Anatolian Natural Gas Pipeline (TANAP) is part of the Southern Gas Corridor, aimed at turning Turkey into an energy hub and diversifying EU natural gas supplies away from Russia.

"Our country is now one step closer to its vision to become a hub of regional energy lines thanks to TANAP," Turkish President Recep Tayyip Erdogan said in the central city of Eskisehir on Tuesday, dubbing the project "the Silk Road of energy."

Azerbaijani President Ilham Aliyev, Ukrainian President Petro Poroshenko and Serbian President Aleksandar Vucic were in attendance at the ceremony which saw the last section of the pipeline put in place.

Friday, June 8, 2018

Italy says mulling late-in-the game changes for massive TAP natural gas project - XINHUA NEWS


2018 JUNE 08, 05:33:26
Eric J. Lyman

ROME, June 7 (Xinhua) -- The future of the ambitious Trans-Adriatic Pipeline (TAP), which aims to give western Europe access to natural gas from Azerbaijan's massive Shah Deniz fields, may be in doubt after leading officials in the new Italian government said the project made no sense for Italy.

Sergio Costa, who was installed as Italian environment minister under Prime Minister Giuseppe Conte less than a week ago, promised to launch a study into whether Italy will benefit from continuing to participate in the so-called TAP project. And Minister of the South Barbara Lezzi expressed worry about environmental risks associated with TAP.

The 4.5-billion-euro (5.4-billion-U.S. dollar) TAP project spans 880 kilometers (550 miles) from the border between Turkey and Greece, across Greece into Albania, under the Adriatic Sea, and into San Foca in the southern Italian region of Apulia. From there, it will link with existing gas infrastructure to reach multiple western European markets.

Friday, April 27, 2018

Giant gas pipeline boost for Turkey amid turmoil - ARAB NEWS




April 27, 201813:10
Richard Wachman
  • Turkey’s aim to become regional energy hub not yet achieved
  • Ankara to collect transit fees, tariffs and taxes
It has been a decade in the making: The $40 billion Southern Gas Corridor (SGC), arguably the gas industry’s most significant and ambitious undertaking yet, involving seven governments and 11 companies.

The 3,500 kilometers pipeline corridor is one of the biggest infrastructure projects in the global oil and gas industry, bringing Caspian gas through three linked networks across Azerbaijan, Georgia, Turkey, Greece and the Adriatic Sea to southern Italy where it can be conveyed to European markets.

SGC has been pushed by the EU since 2008 as a strategic imperative to reduce the bloc’s dependence on Russian gas, and has been bankrolled by EU and international funding, including loans from the Asian Infrastructure and Investment Bank, which counts Saudi Arabia and UAE as members.

Friday, March 30, 2018

Is the TAP, a project of national and geopolitical importance, at stake? - IBNA



30-03-2018, 21:13
Nefeli Tzanetakou

Construction of the Greek section of the Trans-Adriatic Pipeline natural gas pipeline is proceeding rapidly, with the aim of completing the project within the foreseen timetable, that is within 2018.

According to Katerina Papalexandri, the project manager for Greece, the construction from Evros Gardens to the Greek-Albanian borders in Kristalopigi, Kastoria, will have been completed by November 2018.

After that, the testing period is expected sometime by mid-2019, a moment when hydrocarbons will become part of the project, and in 2020 the TAP pipeline will be ready for commercial operation.

The pipeline will initially transfer 10 billion cubic meters of gas a year, from the Shah Deniz deposit in Azerbaijan to Europe, with a potential for doubling the capacity to 20 billion cubic meters, while it will be connected with the Greek gas system at three spots (in Pella, Kastoria and Kozani).

Thursday, March 15, 2018

EIB approves 932 mln euro loan for TANAP gas pipeline - REUTERS


MARCH 15, 2018 / 5:48 PM
Reporting by Alissa de Carbonnel; editing by Philip Blenkinsop

BRUSSELS, March 15 (Reuters) - The European Investment Bank approved 932 million euros ($1.15 billion) in financing on Thursday for the Trans-Anatolian Natural Gas Pipeline (TANAP), the largest part of a $40 billion project to bring new gas supplies to Europe.

The so-called Southern Gas Corridor is expected to bring around 16 billion cubic metres per year to Europe by 2020 from the Shah Deniz 2 field in Azerbaijan via TANAP through Turkey, the South Caucasus pipeline extension through Georgia and the Trans-Adriatic Pipeline (TAP) to Greece, Albania and Italy.

Shah Deniz 2 is one of the world’s largest gas fields and is developed by a BP-led consortium.

Financing for construction of the TANAP pipeline has already been approved by the European Bank for Reconstruction and Development (EBRD), the World Bank and Asian Infrastructure and Investment Bank (AIIB).

Tuesday, February 6, 2018

EIB approves 1.5 bln euro loan for TAP gas pipeline - REUTERS

FEBRUARY 6, 2018 / 7:39 PM
Alissa de Carbonnel, 
Editing by Jane Merriman

BRUSSELS, Feb 6 (Reuters) - The European Investment Bank on Tuesday approved a 1.5 billion euro loan for the Trans-Adriatic Pipeline (TAP), part of a $40 billion project to bring new gas supplies to Europe.

The European Union is trying to reduce its dependence on Russian gas by developing the so-called Southern Gas Corridor which is expected to bring around 16 billion cubic metres of gas per year to Europe by 2020.

The gas would come from the Shah Deniz 2 field in Azerbaijan via several routes, including the Trans-Adriatic Pipeline (TAP) to Greece, Albania and Italy.

TAP is slated to bring up to 10 billion cubic metres of gas to Italy from Shah Deniz 2 - one of the world’s largest gas fields developed by a BP-led consortium.

EIB Vice President Andrew McDowell told Reuters the TAP project would help to offset declining European production, provide a diversified source of gas and displace coal-fired power generation in central and south eastern Europe.

Friday, February 2, 2018

Southern Gas Corridor to Start Pumping Natural Gas in Mid-2018 - CASPIAN NEWS

February 2, 2018
Mushvig Mehdiyev


The Southern Gas Corridor mega-pipeline that will deliver Caspian gas to Europe and Turkey, may come online early and be operational by the middle of this year.

On Thursday, BP’s regional president for Azerbaijan, Turkey and Georgia, Gary Jones, said the development of the second phase of Azerbaijan’s Shah Deniz gas field – currently the only supplier for the corridor – and the expansion of the South Caucasus pipeline – one of three segments within it – are almost complete.

Wednesday, December 6, 2017

Edison takes on Shah Deniz gas supply contract - OFFSHORE MAGAZINE



DEC/06/2017

MILAN, Italy – Edison has agreed to acquire Gas Natural Vendita Italia (GNVI) from Gas Natural Fenosa for Eu192.8 million ($228 million).

GNVI supplied gas and electricity last year to 420,000 residential and 14,000 SME users in Italy.

Under the agreement, Edison will also assume an 11-TWh long-term gas supply contract from the Shah Deniz II development project in the Azeri sector of the Caspian Sea.

Gas imports from the project are set to begin at the end of 2020 following the completion of the Trans Adriatic Pipeline (TAP).

Total consideration payable for the gas supply contract is Eu30 million ($35.5 million), starting from 2021 subject to the first delivery of gas to Italy through the TAP pipeline.

Sunday, May 7, 2017

ADB agrees to lend $500 mln to Azeri gas project - REUTERS

Sun May 7, 2017 | 9:19am EDTReporting by Nailia Bagirova; writing by Andrey Ostroukh; editing by Jason Neely

The Asian Development Bank (ADB) has agreed to provide a $500 million loan to Azerbaijan's Shah Deniz 2 project, the Azeri finance ministry said on Sunday.

The ADB said earlier this year it was considering lending money to Azerbaijan to help fund the second stage of development of the Shah Deniz natural gas project in the Caspian Sea.

On Sunday, the ADB and representatives of Azerbaijan signed an agreement in Yokohama, Japan, under which the Southern Gas Corridor will receive funds to develop Shah Deniz 2, the ministry said in a message sent to Reuters.

Thursday, May 4, 2017

TAP pipeline reports progress through Greece - NEW EUROPE

17:43 MAY 4, 2017
New Europe Online/KG


Security is the project’s absolute priority, TAP says

The Trans Adriatic Pipeline (TAP) on May 4 informed the Embassies located in Greece about the progress of the project, highlighting security as the project’s absolute priority.

The approximately 878 kilometre long TAP pipeline will connect with the Trans Anatolian Pipeline (TANAP) at the Turkish-Greek border at Kipoi, cross Greece and Albania and the Adriatic Sea, before coming ashore in Southern Italy.

TAP’s Country Manager for Greece Rikard Scoufias focused on how TAP is being implemented in Greece with respect to local communities, as demonstrated in the engagement and consultation process followed; the extensive communication campaigns launched; the social and environmental investments programme drafted and implemented; and the benefits TAP brings to Greece – both present and future ones, TAP said in a press release.

Monday, April 17, 2017

Azerbaijan foreign minister, SOCAR vice-president for Malta visit - MALTA TODAY

17 April 2017, 8:31am

The foreign minister of Azerbaijan will lead a delegation in a visit to the Maltese prime minister later on this afternoon, in a three-day visit.

The 6:30pm visit from Elmar Mammadyarov, which includes executives from the state oil and gas company SOCAR, was revealed by Malta Independent columnist Daphne Caruana Galizia. Over the weekend, her allegations of money transfers from an Azerbaijan bank account to the Panama offshore companies held by the PM’s chief of staff Keith Schembri and minister Konrad Mizzi were instantly met with two libel actions.

Saturday, April 8, 2017

Gas Interconnector Greece-Bulgaria (IGB) Pipeline, Bulgaria - HYDROCARBONS TECHNOLOGY

April 2017

Gas Interconnector Greece-Bulgaria (IGB) is a trans-boundary pipeline project involving the construction of a 182km-long natural gas pipeline between Greece and Bulgaria.
PROJECT TYPE: Natural gas pipeline -- LOCATION: Greece-Bulgaria -- START OF CONSTRUCTION: 2018 -- ESTIMATED INVESTMENT:€160m ($170m) -- EXPECTED COMPLETION: 2020 -- LENGTH: 182km -- CAPACITY: Three billion cubic metre a year

Thursday, April 6, 2017

SCPX pipeline network on track for completion next year - UPSTREAM ONLINE

6 Apr 2017 09:47 GMT
Kama Mustafayeva

The Azeri and Georgian pipeline network that will feed Shah Deniz gas to the Trans Anatolian Pipeline (Tanap) is likely to be completed next summer, writes Kama Mustafayeva.

The pipeline, known as SCPX, will be ready to receive production from Shah Deniz 2 in late June next year, according to Tanap managing director Saltuk Duzyol. "We plan to make our first gas delivery at the end of June 2018 if everything goes according to schedule. We are keeping costs relatively low," Duzyol said.

About 77% of the so-called "phase zero" of Tanap , which runs from the Turkish-Georgian border to Eskisehir has already been completed.

Friday, March 10, 2017

10,000 Olive Trees to Be Moved for Gas Pipe in Puglia - OLIVE OIL TIMES / REUTERS

March 10, 2017
Julie Al-Zoubi

Ten thousand olive trees, including some as old as 400 years, will be moved from a UNESCO-recognized olive grove in Puglia, as work on the $40 billion Trans Adriatic Pipeline (TAP) finally gets underway.

On 7th March a TAP spokesman told Reuters, “We’re going to start moving the olives in a few days.” He confirmed that the company had complied with all the regulations required to proceed with uprooting the trees. Work was due to begin on TAP last year but was delayed by strong local opposition including protests.

The spokesman confirmed that administration procedures for the removal of the trees were complete. He added that the required health checks on the trees were underway.