Jun 10, 2019 11:46 EEST
Mario Tanev
SOFIA (Bulgaria), June 10 (SeeNews) - ICGB, the company developing the Gas Interconnector Greece-Bulgaria project, said that it has signed a 5.67 million euro ($6.41 million) contract with the TIBEI consortium, which won the tender for selecting an owner's engineer for the project.
The contract was signed on May 20, according to a notice by the ICGB, published on Friday.
The TIBEI consortium comprises Belgium's Tractebel Engineering S.A, Italy's Tractebel Engineering SRL, Austria's Intber GmbH and Bulgarian companies Ipsilon Consult and Bulgaria Engineering.
"The commitment involves assisting the Contracting Entity in the implementation of the project during the construction phase until the pipeline enters into operation and management of all the main contracts related to the project - including the contract for the supply of line pipes and the contract for the award of design, procurement and construction," ICGB has said previously.
Showing posts with label TIBEI. Show all posts
Showing posts with label TIBEI. Show all posts
Monday, June 10, 2019
Wednesday, April 24, 2019
ICGB selects contractor for supervision for construction of the gas interconnector Greece-Bulgaria - ICGB AD
24/APRIL/2019
The project company finalized one of the last key public procurements to start the construction work for the IGB project
The project company ICGB successfully completed the public procurement procedure with subject “Selection of contractor for construction supervision for the construction of the gas interconnector Greece-Bulgaria”. Three offers were submitted within the announced deadline. The estimated value of the public procurement is BGN 1 300 000 excluding VAT.
The construction supervision will be carried out by the joint venture “EKO BUL CONTROL”, which consists of three legal entities: ECOENGINEERING LTD, BUL STROY CONTROL ENGINEERING and CONTROL ENGINEERING. The selection of a contractor for this procedure is based on the selection criteria price/quality ratio. The total cost for the construction supervision activities for the IGB gas pipeline proposed by “EKO BUL CONTROL” is BGN 766 000 excluding VAT.
"The finalization of this procedure is a great success for the project as the tender for construction supervision is one of the key steps to ensuring the management of the construction in the most professional and efficient way", announced the Executive Officers of ICGB Teodora Georgieva and Konstantinos Karayannakos.
The project company finalized one of the last key public procurements to start the construction work for the IGB project
The project company ICGB successfully completed the public procurement procedure with subject “Selection of contractor for construction supervision for the construction of the gas interconnector Greece-Bulgaria”. Three offers were submitted within the announced deadline. The estimated value of the public procurement is BGN 1 300 000 excluding VAT.
The construction supervision will be carried out by the joint venture “EKO BUL CONTROL”, which consists of three legal entities: ECOENGINEERING LTD, BUL STROY CONTROL ENGINEERING and CONTROL ENGINEERING. The selection of a contractor for this procedure is based on the selection criteria price/quality ratio. The total cost for the construction supervision activities for the IGB gas pipeline proposed by “EKO BUL CONTROL” is BGN 766 000 excluding VAT.
"The finalization of this procedure is a great success for the project as the tender for construction supervision is one of the key steps to ensuring the management of the construction in the most professional and efficient way", announced the Executive Officers of ICGB Teodora Georgieva and Konstantinos Karayannakos.