Friday, March 20, 2020

Energean on course to deliver first gas from Karish field in 2021 - OILFIELD TECHNOLOGY

Friday, 20 March 2020 16:00
Nicholas Woodroof

Energean Oil and Gas plc has announced its audited full-year results for the year ended 31 December 2019 (FY19).
Highlights
  • Karish was 72% physically complete at 31 December 2019 and remains on track to deliver first gas in 1H21. Firm gas sales of 5 billion m3/yr with a further 0.6 billion m3/yr to be converted to a firm basis immediately on publication of a satisfactory Karish North CPR, expected at the end of March 2020.
  • Post-period end, two of the three Karish development wells successfully flowed during clean-up operations, confirming that each will be capable of delivering up to the design limit of 300 mmscf/d (c.3 billion m3/yr). The third development well is currently in the clean-up phase and production performance is expected to be similar, confirming that the three wells will be able to produce to the 8 billion m3/yr capacity of the FPSO.

Thursday, March 19, 2020

Energean on track for first Israeli gas, FPSO sailaway 'in coming weeks' - PLATTS

19 Mar 2020 | 10:54 UTC London
Author: Stuart Elliott
Editor: Alisdair Bowles 

London — UK-based Energean Oil & Gas said Thursday it is on track for first gas from its Israeli offshore fields in the first half of 2021, announcing that the hull of the firm's dedicated production vessel would sail away from its Chinese shipyard "in the coming weeks."

There had been concern that work on the 8 Bcm/year capacity FPSO Energean Power could be delayed due to travel restrictions imposed in China after the start of the coronavirus outbreak.

"In the coming weeks, you will see our FPSO hull sail away from China to Singapore, a key milestone in the delivery of first gas from Karish, which is on track for H1 2021," CEO Mathios Rigas said following the release of the company's 2019 earnings.

Energean said final work on the vessel would take place in Singapore and the vessel sailed to Israel around year-end for installation.