Monday, July 30, 2018

Building New Natural Gas Rig Off Israel's Shores Poses High Ecological Risks, Expert Warns - HAARETZ

Jul 30, 2018 10:07 PMZafrir Rinat 

One of the world’s leading experts on the environmental consequences of gas and oil pollution, Prof. Rick Steiner, is warning of the risks posed by erecting a platform only 10 kilometers from Dor Beach to process natural gas from the Leviathan gas field.

He argued that it isn’t too late to rethink the idea and instead operate a floating platform much closer to the drilling site, which lies over 100 kilometers further from shore.

Steiner spoke Monday at a press conference held by Shomrei Habayit (“Homeland Guards”) an organization representing residents of the Carmel shore region that is battling against the platform’s construction.

Steiner prepared a detailed report for Shomrei Habayit saying that operating the gas platform near the shore increases the likelihood of serious damage to the marine environment and the beach, should there be a malfunction or a hostile attack on the facility.

Steiner criticized the planning and decision-making process. He noted, among other things, that in important documents dealing with the environmental impact of the platform’s activity, large sections were redacted because Noble Energy, one of the partners operating Leviathan, claimed they contained trade secrets.

Thursday, March 2, 2017

Work starts on Leviathan field’s first phase - OIL & GAS JOURNAL

HOUSTON, MARCH/02/2017
By OGJ editors

Wood Group has begun detailed engineering for the 30,000-ton fixed platform to be installed offshore Israel to handle production from deepwater Leviathan natural gas field (OGJ Online, Feb. 23, 2017).

Operator Noble Energy Inc. has drilled two of the four wells to be completed subsea in about 5,200 ft of water during the first development phase. Each will be able to produce more than 300 MMcfd of gas.

Twin 73-mile, 18-in. flowlines will carry production to the platform, which will be set in 270 ft of water about 6 miles from shore.

Can Leviathan Be Prevented From Swallowing Israel's Gas Market? - HAARETZ

Mar 02, 2017 12:50 AM
Avi Bar-Eli 

The field's partners pivoted to the domestic market in response to market shifts, but the government is stuck in 2015 with outdated regulations - and the public will pay the price.


A year ago, the partners in the Leviathan offshore natural gas field made major changes in the plan to develop the reservoir in the wake of the collapse of world energy prices and difficulties finding export markets.

Instead of building a floating offshore platform over the wells they are drilling, capable of handling large quantities of gas for export, they decided to make do, at least in the first stage of development, with using cheaper, more limited means to transport the gas to Israel. The floating platform will wait for the project’s second stage, when the partners hope to sign export contracts with Egypt or Turkey [or Greece/Italy].