Wednesday, 7 December 2016

Eni plans to complete phase one of its USD 4 bn gas processing plant in Port Said next October, Al Borsa reported. The first phase of the plant, which will process gas from Zohr, will produce a daily 650 mcf, which represents 24% of the facility’s total daily capacity upon becoming fully operational of 2.7 bcf. The project should operate at full capacity by 2020 and Eni expects to pump a daily 900 mcf into Egypt’s natural gas network by the end of 2017 or 1Q2018, sources at Eni told the newspaper.